Today the Planning Inspectorate have decided to allow our appeal for the mid-sized wind turbine at Brayton Park, Aspatria in Cumbria.

Previously we had already won an appeal for a similar sized wind turbine at this site but had not been allowed to make any modifications to the permission without submitting a new planning application – which predictably led to refusal by Allerdale planning committee members (despite another recommendation to allow by planning officers) and a hence another appeal.

Residents of Allerdale may perhaps be wondering whether the council is spending their money wisely in their continued obstruction of any and all wind energy related applications. Previously it was leaked that the council had spent 80 thousands pounds fighting (and loosing) multiple appeal cases.

Naturally we are delighted by this decision and look forward to Brayton becoming our 6th operational turbine.

The inspectors decision can be downloaded here.