After a very busy year in which our first two turbines were commissioned, December turned out to be a stellar month with windspeeds well above average over much of the holiday period.

DG001 – Commissioned January 2012

Now running smoothly after some initial teething troubles with local grid instability resulting in frequent shutdowns. A faulty anemometer was replaced in the summer during the scheduled service and more recently some electronic upgrades have been made to the controller. We are now nearing the end of the first full 12 months of production with high expectations for the next year!

DG002 – Commissioned November 2012

Summer 2012 wet weather made construction and installation a nightmare with on-site conditions resembling a swamp at times. As a result the build took much longer than predicted with final commissioning delayed until the Autumn. Our luck did not improve when the failure of a nearby substation caused a power surge which damaged some components in the turbine controller. These were replaced and extra fuse protection has now been installed (also at DG001) to prevent any re-occurrence. Service technicians recently undertook the 500hr “shakedown” and pronounced a clean bill of health.

Some minor damage to the turbine door lock was discovered and a CCTV system has now been installed as a precaution.

DG003/DG004 – Scheduled for installation Summer-Autumn 2013

Pre-installation project development continues with connection and power purchase agreements at both sites.

Planning

Planning appeals at both Apex and Talbot Farm are now well under way with final submissions having been made to the Planning Inspectorate. A further appeal at Brayton Park (for a modification to an existing permission) will be submitted very shortly with every expectation that it will be allowed as per the original appeal.